This project consists of improving the intersection of Butler-Warren Road and Western Row Road (Barret Road) from a stop controlled intersection to a roundabout intersection with curb and gutter, proper storm drainage, sidewalk, culvert replacement, and utility relocation.
Public Involvement Exhibits:
Project Timeline:
Design: 2017 to 2020
Right of Way: 2019-2020
Construction: Spring/Summer 2021
Current Status: Working on Right of Way acquisition for the project and utility relocation coordination as well as Stage 3 plan design.