This improvement project generally consist of reconstruction of the soccer fields, work includes mass grading, sanitary sewer and water line relocation, storm sewer and underdrain installation, asphalt and concrete installation and addition of an irrigation system.
Project Timeline:
Design: 2019
Construction: Summer 2019 – Spring 2020
Current Status: Contractor is working on installing irrigation in and final grading in preparation for seeding and mulching this coming spring.