This project will change two existing stop controlled “T” intersections (stop controlled on Bethany Rd and Mason-Morrow-Millgrove Rd, free flow on US 42) to roundabouts. Project limits for the project are approximately 400-feet each direction from the intersections, the project will also widen US 42 between the two intersections to a 3-lane section. A multi-use path is also included in the project that will connect from SR 741 to US 42 along Bethany Rd, then along US 42 to Mason-Morrow-Millgrove Rd and then along Mason-Morrow-Millgrove Rd to an existing path in the Mason Sports Park. Roadway improvements include storm sewers, multi-use path, sidewalk, curb and gutter, lighting, and utility relocation.
Preliminary Layout
Project Timeline:
Design: 2019 to 2021
Right of Way: summer 2020 – Summer 2021
Construction: Spring 2022
Current Status: Working on Stage 2 plans and right of way plans.