Phase 2
This Warren County Transportation Improvement District (WCTID) project is expected to begin construction this spring and continue to approximately summer 2019. A full interchange with northbound on-and-off-ramps, as well as southbound on-and-off-ramps will be built at the I-71 & Western Row Road Interchange. Currently there is only a partial interchange, with northbound exit ramp and a southbound on-ramp, at the completion of this project, there will be on-and-off-ramps for both north and southbound traffic. Specifically, there will be a new southbound off-ramp and on-ramp connecting directly to Innovation Way, as well as two new northbound on-ramps from eastbound and westbound Western Row Road.
More info about this work can be found at ImagineWesternRow.com, and on Facebook and Twitter at https://www.facebook.com/imaginewesternrow/ and https://twitter.com/WesternRow71.